  1. Discovery.  January 2010 – May 9, 2010.
  2. Downtown Neighborhoods Design Visioning and Design Workshop.  May 10 – 15, 2010.
  3. Downtown Neighborhoods ”Unpacking”.  June, 2010. 
  4. Downtown Neighborhoods Community Plan Preparation.  July, 2010 - June 2012
  5. Environmental Review.  Fall 2011 – Summer 2012. 
  6. Public Hearings and Plan Adoption.  Fall 2012      

 

Fulton Corridor Specific Plan

  1. Discovery.  January 2010 – May 2010.
  2. Fulton Corridor Design Visioning and Design Workshop.  September 25 – October 2, 2010.
  3. Fulton Corridor ”Unpacking”.  October, 2010. 
  4. Fulton Corridor Specific Plan Preparation.  November 2010 - June 2012.
  5. Environmental Review.  Fall 2011 – Summer 2012. 
  6. Public Hearings and Plan Adoption.  Fall 2012.