- Discovery. January 2010 – May 9, 2010.
- Downtown Neighborhoods Design Visioning and Design Workshop. May 10 – 15, 2010.
- Downtown Neighborhoods ”Unpacking”. June, 2010.
- Downtown Neighborhoods Community Plan Preparation. July, 2010 - June 2012.
- Environmental Review. Spring 2012 – Winter 2013.
- Public Hearings and Plan Adoption. Spring 2013.
Fulton Corridor Specific Plan
- Discovery. January 2010 – May 2010.
- Fulton Corridor Design Visioning and Design Workshop. September 25 – October 2, 2010.
- Fulton Corridor ”Unpacking”. October, 2010.
- Fulton Corridor Specific Plan Preparation. November 2010 - June 2012.
- Environmental Review. Spring 2012 – Winter 2013.
- Public Hearings and Plan Adoption. Spring 2013.